Metropolitan Electricity Authority details construction plans for Nonthaburi underground power cable project, targeting March 2026 completion.
The Metropolitan Electricity Authority (MEA) has outlined detailed construction plans for its underground power cable project in Nonthaburi province, specifying work on various major roads.
This initiative aims to enhance the reliability and aesthetics of the urban power grid by removing overhead lines, contributing to modernized infrastructure and improved quality of life for residents.
Fast Facts
·Project: Underground power cable system conversion
·Location: Nonthaburi Province, Thailand
·Planned completion: March 2026 (Buddhist Era 2569)
·Total project length: 23.2 kilometers
·Key roads involved: Tiwanon, Chaeng Watthana, Rattanathibet, Bangkok-Nonthaburi, Nakhon In, Wong Sawang, Vibhavadi Rangsit, Ratchaphruek-Kanchanaphisek